Delectrik Systems, a Gurugram-based vanadium flow battery developer, has won a 120 MWh utility-scale vanadium flow battery project in Gujarat, India. The award was made in the latest round of the battery energy storage system (BESS) tender issued by Gujarat Industries Power Company Limited (GIPCL). Bondada Engineering Limited is the associate on the project.

Second utility-scale award this year

The GIPCL contract is Delectrik's second utility-scale flow battery project of 2026. Its first was a 100 MWh flow battery project for NTPC Renewable Energy Limited, which is currently under execution. The two awards together represent 220 MWh of utility-scale vanadium flow capacity associated with the company's pipeline, with one project already in delivery and the other newly secured.

For the flow battery segment, a 120 MWh award from a state-owned generator is a notable scale marker. Utility storage procurement has been overwhelmingly lithium-ion to date, so each large non-lithium award adds a reference plant that future tenders can point to.

Why duration matters in this procurement

Vanadium flow batteries store energy in liquid electrolyte held in external tanks, so capacity is scaled by adding electrolyte volume rather than additional cells. That architecture is generally positioned for multi-hour duty cycles, where a system is expected to charge and discharge for extended periods rather than deliver short bursts of power. The GIPCL award, sized in megawatt-hours rather than megawatts, is consistent with that long-duration use case.

Local engineering partnership

The involvement of Bondada Engineering Limited as associate on the project indicates a consortium-style delivery structure, pairing flow battery technology with an engineering partner on the ground. Such arrangements are common in Indian utility storage procurement, where balance-of-plant, civil works and grid interface work sit outside the core battery scope.

What is not yet public

The reporting does not disclose the contract value, the tariff or capacity charge agreed with GIPCL, the delivery schedule, or the intended site within Gujarat. Nor is the duration of the storage system in hours specified. These details typically emerge as projects move into construction and are formalised in power purchase or storage agreements.

The NTPC Renewable Energy project, at 100 MWh, remains under execution, meaning Delectrik is currently running one large utility build while starting a second. Execution capacity — not order intake — is likely to be the constraint that determines how quickly either project reaches commercial operation.